The Single Tender Commission of MBC Corporation has held meeting
A meeting of the Single Tender Commission of MBC
Corporation (Metals of Eastern Siberia) chaired by Deputy Director
General S.N. Garichev was held on March 29, 2010. The Single Tender Commission was established to
conduct tenders for design works related to the construction of the
Ozyornyy Ore Dressing Plant and other projects managed by the MBC
Corporation. The company plans by mid-April 2010 to announce
tenders to complete the following works:
1. Clearing of trees to build an ore storage facility and a road
between the quarry and the field camp
2. Earthworks (for construction) and mining
3. Comprehensive engineering survey of the Ozyornyy Ore Dressing
Plant and its infrastructure
The tenders are held in an open manner. All the necessary
information will soon be posted on the website of MBC Corporation
under “Tenders.”
The pre-tender work for the supply of complete turnkey mining
equipment, construction of the mining beneficiation plant and
combined heat and power plant (CHP) is continuing in accordance
with the procedures previously
declared on MBC Corporation’s website.
The Group includes six battery plants and business units developing and introducing new technologies, and distributing products.
№ 077-06136-100000, № 077-06159-010000, № 077-06168-001000 from 26 august 2003 year, № 077-06194-000100 from 02 september 2003 year, № 650 from 16 april 2004 year, № 3185 from 25 november 1999 year, № 21-000-1-00119 from 23 may 2003 year, № 077-07215-001000 from 9 december 2003 year